Chill Factor E, Manchester |
| Type of Works | Area | Contract Period | | Safety net system by rope access | 20,000m² | 9 Months | | Temporary edge protection | 380m | | | Access stair towers | 3 x 16m | | | Installation of safety lines by rope access | | | | Painting works by rope access | | | | Installation of signage and posters by rope access | | |
http://www.chillfactore.com/ HASL installed and dismantled the full safety net system and access towers to the new indoor ski and activity centre at Trafford Park in Manchester. Along with the safety net system HASL supplied and installed temporary edge protection to the various roof areas. HASL also completed poster installations and cleaning works during the contract period and concluded the project with large scale cleaning and painting works to the roof steelwork. ... ... ... ... ... ... ... ... |