Colmore Plaza, Birmingham |
| Type of Works | Area | Contract Period | | Installation of Combisafe Net Fan System | 2 floors | 12 Months | | Mini-crane lifting equipment | | | | Re-installation of subsequent floors | | | HASL were approached by Bowmer & Kirkland on the prestigious Colmore Plaza project in Birmingham to provide a debris protection system which would allow for other works to carry on undisturbed below. HASL in association with Combisafe designed and installed a Combisafe Net Fan system to level 1 consisting of over 50 safety net fans. The installation was undertaken using a mobile mini-crane to reduce down time for the tower crane. HASL further dismantled the system and re-installed on the eighth floor as the structure progressed. Please follow this link for net fan products. ... ... ... |